bangladesh rooppur unit 1 fuel loading

A major milestone for Bangladesh’s nuclear energy ambitions has arrived. On April 16, the Bangladesh Atomic Energy Regulatory Authority (BAERA) granted a commissioning licence to Rooppur Unit 1, allowing fuel loading to begin. BAERA Chairman Mahmudul Hasan handed the licence to BAEC Chairman Dr M Moinul Islam after rigorous review by national and international regulatory bodies. The approval came only after all required technical tests and preparatory work were completed successfully. The licence grant followed satisfactory completion of required processes as mandated by regulatory standards.

Fuel loading is now scheduled to begin on April 28. The original target date of April 7 was missed while waiting for regulatory clearance. Despite the delay, the Bangladesh Atomic Energy Commission (BAEC) expects the process to start by month’s end. Loading the fuel is expected to take approximately one month. This timeline follows Rosatom’s notification of the schedule to the government.

Fuel loading at Rooppur Unit 1 begins April 28, delayed from April 7 while awaiting regulatory clearance, with completion expected within one month.

The project has reached this stage through several important preparatory milestones. Boron flushing of the primary circuit piping was completed in 81 hours, confirming the reactor’s readiness for physical start-up. Dummy fuel assemblies were reportedly used for hydraulic validation testing in late 2024. The turbine installation finished in March of the previous year. Hydraulic and hot functional tests were finished before the boron flushing began. The project faced multiple delays in recent years, including effects from Covid-19 and war-linked complications.

Once fuel loading concludes, power generation won’t happen immediately. Criticality—when the nuclear chain reaction starts—should occur roughly two months after fuel loading begins. The reactor is expected to deliver 300 megawatts of electricity to the grid by late July or early August. Full capacity of 1,200 megawatts is targeted for December. Grid connection represents a key target for Rosatom this year.

Rooppur represents Bangladesh’s first nuclear power plant. Located in Ishwardi Upazila on the Padma River, 160 kilometres northwest of Dhaka, the facility houses two VVER-1200 reactors. Each reactor produces 1,200 megawatts, totalling 2.4 gigawatts. Unit 1 is now in final commissioning, while Unit 2 is over 70 percent complete. The project originally faced a three-year delay from its 2022 target. A 2025 agreement with Russia extended the timeline to late 2027 for both units. Rooppur’s progression reflects a broader global trend, with roughly over 70 gigawatts of new nuclear capacity currently under construction worldwide.

✅ Claims in this article were verified using AI-assisted fact-checking.

References

You May Also Like

After the Shutdown: U.S. Solar Cell Manufacturing Returns After 5-Year Gap

After 5 years of zero domestic production, America’s solar factories are roaring back—but one giant just pulled the plug on expansion plans.

Massachusetts Solar Homeowners Trapped in Deceptive Leases With Escalating Payments and Failed Systems

Massachusetts homeowners promised “free” solar panels now face decades of escalating payments and non-functioning systems. What solar companies aren’t telling you.

TotalEnergies Abandons US Offshore Wind for $1 Billion Taxpayer Payout With No Disclosed Funding Source

TotalEnergies abandons U.S. offshore wind for $1 billion taxpayer payout. Where’s the money coming from, and what does it mean for clean energy?