Data centers in Virginia are hungry for power — and the numbers are staggering. Companies have asked Dominion Energy for 70,000 megawatts (MW) of electricity. That’s nearly three times Virginia’s all-time peak demand of 24,678 MW, which was set during a cold spell on January 23, 2025.
Of those requests, 25,000 MW are tied to facilities planning to connect by the end of 2031. Another 45,000 MW have no set dates. On average, Dominion receives about 10 new requests per month, adding up to 2,000 to 3,000 MW each time. As of December 2024, about 40,000 MW of requests were linked to data centers.
Virginia’s already a data center hotspot. The state hosted 451 data centers using 3,583 MW in 2024. Data centers grew to represent around a quarter of Virginia’s total electricity sales by 2024. In 2023 alone, 15 new data centers added 933 MW of capacity. A small number of Dominion’s largest customers, likely data centers, account for a majority of recent demand growth.
To keep up, Dominion’s investing heavily. The company is committing tens of billions, including for data center growth and clean energy. Plans include multi-billion-dollar high-voltage transmission lines. Dominion’s also putting $10 billion into a 2.6 gigawatt offshore wind project off Virginia’s coast.
Northern Virginia’s long been the center of data center growth, but the grid there’s under strain. Companies are now expanding to Chesterfield County, where a 900 MW campus is planned. Dominion’s also working with partners to bring data centers to Southwest Virginia.
Managing all of this growth hasn’t been simple. Dominion shifted to a formal system for handling large power requests. The State Corporation Commission directed Dominion to explain this process in November. New rules also shift some infrastructure costs directly to data centers through 2033.
Tech giants like Microsoft and Google have reserved participation rights in Dominion’s system. Requests for newer campuses reportedly range from hundreds of MW to gigawatts — a sharp jump from earlier, smaller projects. Dominion has pursued nuclear collaborations, including with tech firms, for future capacity. Dominion currently serves more than 2.7 million electric customers in Virginia, making the scale of data center demand even more striking against the backdrop of its broader residential and commercial base.
References
- https://virginiabusiness.com/dominion-data-center-power-demand-virginia-scc/
- https://enkiai.com/data-center/dominion-energys-2026-pivot-taming-data-center-demand
- https://www.in.gov/iurc/files/1.-Data-Center-Forecasting.pdf
- https://wtop.com/virginia/2026/02/virginia-bill-would-put-more-energy-costs-on-data-centers-slash-rates-for-residents/
- https://finimize.com/content/dominion-doubles-down-on-data-centers-but-its-2026-view-fell-short
- https://www.axios.com/local/richmond/2026/02/19/virginia-data-centers-power-electric-bill
- https://www.vpm.org/news/2026-02-10/louise-lucas-data-center-infrastructure-costs-dominion-energy-apco-scc-pjm-virginia