maryland transmission costs soar data centers dodge

Why have Maryland residents‘ electricity bills skyrocketed? Transmission costs—the fees to transport electricity across power lines—have increased five to six times since 2010 for many Maryland households. Now, new data shows that much of this burden falls unfairly on Maryland ratepayers while data centers in other states avoid paying their share.

Transmission costs for Maryland residents have surged five to six times since 2010, with out-of-state data centers unfairly escaping their share.

Maryland customers have been allocated $2.7 billion in capital costs for transmission projects from 2010 to 2030. An additional $5.4 billion is estimated for 2031 to 2035. These massive expenses stem from aging infrastructure, inflation, and supply chain problems. But there’s another major driver: data centers.

Data centers—massive facilities that store and process digital information—are consuming enormous amounts of electricity. Northern Virginia and Ohio have seen explosive data center growth. The PJM regional grid forecasts a 42% peak demand increase across its territory, compared to just 12% in Maryland. Yet Maryland’s residents are paying a disproportionate share of the costs.

Between 2010 and 2030, Maryland has been assigned $7.1 billion in transmission capital costs. That’s problematic because Maryland is reportedly responsible for only a small portion of the region’s load growth. Meanwhile, the state’s paying roughly 10% to 8% of baseline transmission projects in 2029 to 2030. Proposed upgrades for Virginia data centers alone could cost Marylanders an estimated $500 million. The Maryland ratepayer advocate has warned that transmission costs are rising amid broader regulatory scrutiny nationwide.

This cost allocation problem isn’t new. The Office of the Public Counsel, Maryland’s consumer advocate, has challenged PJM’s cost assignments multiple times. In August 2025, the OPC contested BGE’s $634 million in incentives for Virginia data center-related projects. In February 2026, the office filed to investigate BGE’s Baltimore Peninsula transmission costs. Competitively procured projects cost significantly less than baseline projects exempt from competitive bidding, which are on average four times more expensive.

The situation’s complicated by forecast uncertainty. Data center load predictions remain highly uncertain, which means Maryland might be paying for unnecessary infrastructure. The eight-year interconnection backlog also strains the grid, forcing expensive delays.

Maryland residents continue bearing the financial weight while out-of-state data centers benefit from the infrastructure. Transmission costs now comprise roughly the same portion of residential bills as capacity market costs. Without reform, these expenses will continue stretching across decades, affecting electricity bills for years to come.

✅ Claims in this article were verified using AI-assisted fact-checking.

References

You May Also Like

Coal River Mountain Mountaintop Removal Permit Halted by Federal Judge Under Clean Water Act

Federal judge halts mountaintop removal permits, citing Clean Water Act violations. But the coal industry fought back—and won on appeal.

Trump Pays $1 Billion to Kill Offshore Wind Projects While Fourth Developer Sues Administration

Trump administration pays $1 billion to halt offshore wind while fossil fuels get the investment boost. What taxpayers are really funding.

Centralia Coal Plant Defies Trump’s Order, Shuts Down Despite Federal Demand

Centralia coal plant went dark despite a federal emergency order to keep burning coal. Now a fierce legal battle could reshape America’s energy future.

Supreme Court Keeps Michigan’s Line 5 Pipeline Shutdown Fight in State Court After Enbridge Missed Critical Deadline

Michigan’s Line 5 pipeline fight stays in state court after Enbridge’s costly blunder. Will the aging pipeline finally face justice?